Background
Capital Industries, Inc. (Capital) is at 5801 3rd Avenue South in Seattle, Washington, and has occupied this location since 1965. Capital conducts metal fabrication and related work (e.g., metal fabricating, painting).
Former operations at Capital resulted in releases of the chlorinated solvent trichloroethene (TCE) at Plant 2 and TCE with the chlorinated solvent tetrachloroethene (PCE) at Plant 4. TCE, PCE, and their degradation products are collectively referred to as chlorinated volatile organic compounds (CVOCs). These releases have affected soil and groundwater at Capital and groundwater down-gradient (south/southwest) of Plant 2 and Plant 4.
Capital and the Washington State Department of Ecology entered into Agreed Order No. DE 5348 (Agreed Order) on January 24, 2008. Under the Agreed Order, the Capital Site is defined as the area where concentrations of CVOCs released from the Capital Property exceed regulatory cleanup levels. Capital has completed a Remedial Investigation to determine the nature and extent of CVOCs associated with the releases from Capital in the environment and to collect sufficient information to enable development and evaluation of technically feasible cleanup alternatives in accordance with Sections 360 through 390 of Chapter 173-340 of the Washington Administrative Code. The Agreed Order, Public Participation Plan, Remedial Investigation Work Plan, Remedial Investigation Report, and documents associated with the Remedial Investigation may be viewed below.
The nature and extent of CVOCs in soil and groundwater at Plant 4, which is the plant furthest to the east, suggest that a release(s) of TCE and/or PCE may have occurred from degreasing operations and drum storage. The Remedial Investigation work did not detect residual concentrations of CVOCs in soil that suggested an extensive or significant release of CVOCs at Plant 2 or the Plant 2 Canopy. Nevertheless, groundwater data indicate a minor source of CVOCs is likely present. Soil beneath Plant 2 was excavated for the foundation and utility trenches for reconstruction of Plant 2 in 2004 following the destruction of the building by a fire.
Sufficient sampling was performed during the Remedial Investigation phase of work to estimate the distribution of CVOCs in the affected media. All Remedial Investigation work was completed by 2014. In April 2014 Capital entered into a second Agreed Order with other Potentially Liable Persons (PLPs) with co-mingling sources of CVOCs to complete a joint Feasibility Study and Cleanup Action Plan. This group of PLPs now comprise the West of 4th Site, which has a website where interested parties may view the project progress under the new Agreed Order. The new Agreed Order is also available for viewing and download below.
The Feasibility Study work will continue through 2019 and will involve pilot testing of potential cleanup technologies. Capital is testing cleanup technologies that may be applied as an interim action at Plant 4 to address the minor release of PCE and TCE that is affecting groundwater and represents a potential risk to indoor air quality in the northernmost building at the east-adjacent Pacific Food Systems property. A vapor intrusion mitigation system is operating at the Pacific Food Systems north building to mitigate TCE in indoor air. A second vapor intrusion mitigation system currently operates at the Natus Medical building located southwest of Plant 2. This vapor intrusion mitigation system was installed to mitigate potential indoor air impacts associated with a commingled TCE plume originating from Plant 2 and the Blaser Die Casting facility located immediately northeast of Plant 2.
Updates regarding ongoing and planned work activities for Capital are included below in the quarterly progress reports provided to the Washington State Department of Ecology. Details regarding activities for the other PLPs are found on the West of 4th Site web page referenced above.
Agreed Orders
- 2014 Feasibility Study and Cleanup Action Plan Agreed Order
- 2008 Remedial Investigation Agreed Order
- Exhibit A
- Exhibit B
- Exhibit C
- Exhibit D
Public Participation
Remedial Investigation Program
Remedial Investigation Data Gap Resolution Summary Report
Final Remedial Investigation Report
- Ecology Conditonal Approval of RI Letter – December 18, 2012
- Final RI Report October 2012 – Text, Tables, Figures
- Appendix A Boring and Well Construction Logs
- Appendix B through D
- Appendix E Laboratory Reports
- Appendix F through I
Remedial Investigation Work Plan
- Remedial Investigation Work Plan – No Appendices
- Appendix A: Reconnaissance Sampling and Analysis Plan
- Appendix B: Quality Assurance Project Plan
- Appendix C: Health and Safety Plan
- Remedial Investigation Work Plan
- Appendix D: Boring and Well Construction Logs
- Appendix E: Soil Vapor and Gore Sorber Sample Locations and Analytical Results
- Appendix F: BIOCHLOR Modeling Approach
- Appendix G: Second Avenue South Redevelopment Area Laboratory Analytical Reports
Remedial Investigation Work By Others
- 2004 Floyd Snider McCarthy, Inc. Soil Vapor and Construction Monitoring Report
- 2005 Environmental Consulting Services, Inc. Draft Remedial Investigation Report
Tier I Reconnaissance Sampling Results Tech Memo
- Draft Tier 1 Reconnaissance Sampling Results Tech Memo
- Revised Tier 1 Reconnaissance Sampling Results Tech Memo
RI Field Program First Phase Report
- Draft Remedial Investigation Field Program First Phase Report
- Appendix B: Laboratory Analytical Reports
- Ecology Approval Letter for Remedial Investigation Field Program First Phase Report
Vapor Intrusion Program
- 2020 Annual Vapor Intrusion Mitigation Status Report
- Vapor Intrusion Assessment Work Plan
- Vapor Intrusion Mitigation Work Plan, Olympic Medical Facility
- Vapor Intrusion Mitigation Design Plan, Olympic Medical Facility
- Vapor Intrusion Mitigation Report, Olympic Medical Facility
- Vapor Intrusion, Inspection, Monitoring, and Maintenance Work Plan
- Vapor Intrusion Tier 2 Assessment
- Tier 3 VI Assessment – Sampling and Analysis Plan – 5801 3rd Ave S QC and Laser Office
- Tier 3 VI Assessment – Sampling and Analysis Plan – 5801 3rd Ave S Shipping Office
- Tier 3 VI Assessment – Sampling and Analysis Plan – 5807 4th Ave S
- Tier 3 VI Assessment – Sampling and Analysis Plan – 5815 4th Ave S Northern Building
- Tier 3 VI Assessment – Sampling and Analysis Plan – 5815 4th Ave S Southern Building
- Tier 3 VI Assessment – Sampling and Analysis Plan – 5914 4th Ave S
- Tier 3 VI Assessment – Sampling and Analysis Plan – 5930 1st Ave S
- Tier 3 Vapor Intrusion Assessment Report – 5815 4th Ave S Northern Building (2014)
- Vapor Intrusion Mitigation Plan – 5815 4th Ave S Northern Building (2014)
- Vapor Intrusion Inspection, Monitoring, and Maintenance Work Plan: Pacific Food Systems North Building – November 2015
- Vapor Intrusion Mitigation Measures Status Report (DRAFT): Pacific Food Systems North Building – August 2017
- Response to North Building VI Work
- Landau Capital Vapor Intrusion Mitigation Status Report – February 2021
- Landau Capital Vapor Intrusion Work Plan – February 2022
- Landau Capital Vapor Intrusion Mitigation Status Report – March 2022
Groundwater Monitoring Program
- Groundwater Monitoring Plan
- DRAFT Addendum to Groundwater Monitoring Plan
- Tidal Study and Aquifer Characterization Results
- Draft September 2011 Groundwater Monitoring Plan
- Revised 2013 Groundwater Monitoring Plan Addendum
Progress Reports
- January through March (Q1) 2008
- April through June (Q2) 2008
- July through September (Q3) 2008
- October through December (Q4) 2008
- January through March (Q1) 2009
- April through June (Q2) 2009
- July through September (Q3) 2009
- October through December (Q4) 2009
- January through March (Q1) 2010
- April through June (Q2) 2010
- July through September (Q3) 2010
- October through December (Q4) 2010
- January through March (Q1) 2011
- April through June (Q2) 2011
- July through September (Q3) 2011
- October through December (Q4) 2011
- July through September (Q3) 2012
- January through June (Q1 and Q2) 2014
- June through September (Q3) 2014
- October through December (Q4) 2014
- January through March (Q1) 2015
- April through June (Q2) 2015
- July through September (Q3) 2015
- October through December (Q4) 2015
- January through March (Q1) 2016
- April through June (Q2) 2016
- July through September (Q3) 2016
- October through December (Q4) 2016
- January through March (Q1) 2017
- April through June (Q2) 2017
- July through September (Q3) 2017
- October through December (Q4) 2017
- January through March (Q1) 2018
- April through June (Q2) 2018
- July through September (Q3) 2018
- October through December (Q4) 2018
- January through March (Q1) 2019
- April through June (Q2) 2019
- July through September (Q3) 2019
- October through December (Q4) 2019
- January through March (Q1) 2020
- April through June (Q2) 2020
- July through September (Q3) 2020
- October through December (Q4) 2020
- January through March (Q1) 2021
- April through June (Q2) 2021
- July through September (Q3) 2021
- October through December (Q4) 2021
- January through March (Q1) 2022
- April through June (Q2) 2022
- July through September (Q3) 2022
- October through December (Q4) 2022
- January through March (Q1) 2023
- April through June (Q2) 2023
- July through September (Q3) 2023
- October though December (Q4) 2023
- January through March (Q1) 2024
Interim Action
- 2018 CI Plant 4 Field Implementation Work Plan DFAR
- 2017 Interim Action Work Plan
- Revised CI Plant 4 Stage 1 Field Implementation Work Plan
- Final Capital Industries Plant 4 Interim Action – Stage 1 In-Situ Chemical Oxidation Report
- 2019 Soil Vapor Extraction Pilot Test Schedule
- 2019 Final Capital Industries Plant 4 Soil Vapor Extraction Pilot Test Work Plan
- October 25, 2019 Ecology SU2 Interim Action Desist Letter